Jackson Ditch Road over Browns Branch (BR 2-429A)

Project Limits:

200 feet north and south of bridge

Project Need

This bridge consists of severely corroded corrugated metal pipes (CMPs). As such, it is structurally deficient and was selected by the Pontis Bridge Management System for replacement

Project Overview:

Replace the deteriorated CMPs with a precast concrete frame. Construction will be completed in one stage with a detour. Reconstruct approaches and place a scour countermeasure in the stream to protect the structure.

Current Project Schedule:

Design Phase:

Design work completed in October 2011.

Construction Phase:

Construction work to start in May 2012 and be complete within approximately 40 days of beginning.

PROJECT INFORMATION
 
 
PUBLIC FEEDBACK
Public Relations This link opens an email client
302.760.2080
800.652.5600 (DE only)

Jason McCluskey, P.E. This link opens an email client
Project Manager
302.760.2250
 
 
 
Last Updated: Wednesday, 04-Apr-2012 11:32:12 Eastern Daylight Time
site map   |   about this site   |    contact us   |    translate   |    delaware.gov