|
Project Need
Need for this project is founded in an existing roadway system
that lacks capacity for current and future traffic volumes and that has had
sections appear almost yearly on DelDOT's list of High Accident locations.
Earlier studies, indicated below, also identified the lack of capacity and
safety concerns on the existing roadway system in the project area.
Considerable long-haul truck traffic that mixes with increasing automobile
traffic in the project area and growth in population, employment and
dwelling units has only added to the need to provide additional roadway
capacity in the project area. This increased growth, without additional
roadway capacity, places more vehicles on the same roadways every day,
increasing the volume of vehicles and also increasing the potential for
accidents to occur.
The 3 key components that the US 301 Project is addressing are managing
truck traffic, improving safety and reducing roadway congestion.
Project Background
The US 301 Project Development effort began in early 2005. A
comprehensive public outreach and involvement program has been an integral
element of this project, from the beginning. The Department started by
developing a Project Purpose and Need document and a Potential Range of
Alternatives that were presented to the public at workshops on June 20 and
21, 2005. Over 800 people attended these workshops and over 450 comments
were received. During July and August, community meetings were held with a
number of communities impacted by the Potential Range of Alternatives.
Public workshops were subsequently held on September 12, 13 and 19, 2005 at
which the Range of Alternatives was presented. Approximately 1,100 people
attended these workshops and over 1,050 comments were received.
On December 5, 6 and 7, 2005, the Department conducted public workshops at
which the Recommended Alternatives Retained for Detailed Study (ARDS) were
presented. The five ARDS included the Yellow Alternative, the Brown
Alternative, the Green + Spur Alternative, the Purple + Spur Alternative,
and the No Build Alternative. The Green and Purple Alternatives included a
Spur Road to the Summit Bridge to accommodate the traffic with an origin or
destination north of the Summit Bridge. Additionally, both the Brown and
Green Alternatives had both a north and a south option. Over 525 people
attended the workshops and over 500 comments were received. During January
and February, 2006, community meetings were held with a number of
communities affected by the ARDS. The Spur Road was presented at these
community meetings and specific questions about the Spur Road were asked by
those affected communities.
On February 22 and 23, 2006, the DelDOT conducted public workshops at which
the ARDS (including the Green North + Spur) and issues from the December,
2005 workshops were presented. One of the specific issues presented at the
February, 2006 workshops was “What is the purpose and need for the Spur
Road?” Approximately 400 people attended these workshops and approximately
50 comments were received.
On April 10 and 11, 2006, the DelDOT conducted public workshops at which the
Refined ARDS (including the Green North + Spur) were presented.
Approximately 350 people attended these workshops and approximately 150
comments were received.
On January 8 and 9, 2007, the DelDOT conducted public workshops/hearings at
which the Recommended Preferred Alternative (Green North + Spur) and the
Draft Environmental Impact Statement were presented. Approximately 450
people attended these workshops, approximately 45 people provided oral
testimony, and 120 comments were received.
In May 2007, the DelDOT announced the selection of the Preferred Alternative
for the US 301 Project, Green North + Spur Road.
In November 2007, the Final Environmental Impact Statement was circulated,
with the Green North + Spur Road indicated as the Preferred Alternative.
On April 30, 2008, the Federal Highway Administration (FHWA) approved the
Record of Decision (ROD) for the US 301 Project and the Selected
Alternative, Green North + Spur Road. This is the final FHWA approval of the
selected alternative and is necessary in order to secure FHWA authorization
to begin final design (preparation of construction contract/bidding
documents) and the acquisition of right-of-way.
In June 2008, FHWA authorized right-of-way acquisition for the US 301
Project Selected Alternative, Green North + Spur Road.
In June 2008, the General Assembly provided the Department with the
following Bond Bill Epilogue Language:
"The General Assembly directs the Department to implement the US 301
Corridor project in Phases, beginning with the US 301 mainline section.
Before expending funds for the final design and construction of the Spur
Road segment of the project, the Department will convene public workshops on
the Spur Road segment. At the workshops, the Department will present
information and alternatives for the Spur Road, including the upgrading of
the existing US 301. The most current traffic data available at that time
shall be presented to the public at the workshops. The Department shall
report to the General Assembly on the comments received at the public
workshops and make recommendations on how to proceed with this segment of
the project no later than May 1, 2009."
In September 2008, FHWA authorized Final Design (preparation of construction
contract documents) for the Selected Alternative, Green North + Spur Road.
While right-of-way acquisition and final design activities got underway on
the New US 301 Mainline section of the project, neither activity was
initiated on the Spur Road section of the project, due to the 2008 General
Assembly Bond Bill Epilogue language.
In March 2009, the Department presented the required information and
alternatives for the Spur Road at a series of pre-workshop community
meetings and at a March 23, 2009 public workshop. A majority of the comments
received during the community meetings, the workshop and the subsequent
comment period supported the Spur Road over the other alternatives. There
was less support for Alternative 2 (the upgrade of existing U.S. 301); and
there was virtually no support for the "No Build" Alternative 1 (no Spur
Road and no upgrade of existing U.S. 301) and Alternative 3 (shift the
limited access Spur Road to the east, along existing U.S. 301). The
Department also took advantage of the workshop to present a number of
potential refinements to the public (see the website homepage, Final Design
and Right-of-Way Acquisition, regarding the adoption of the refinements).
On April 30, 2009, the Department provided the General Assembly with a
report, which included the comments received at the public workshop and a
recommendation to proceed with the Green North + Spur Road Alternative,
previously approved by the Federal Highway Administration (FHWA) in their
April 30, 2008 Record of Decision (ROD). The Department further recommended
completing final design and right-of-way acquisition for the entire project.
In August 2009, the Department initiated final design activities on the Spur
Road segment of the U.S. 301 project.
|
|